Eighth Ave. NW and 26th St. NW Paving - District No. 2240

About the Project


This multi-phase project involves utilities, a storm water retention pond, and paving. The project will include paving of Eighth Avenue NW from Ninth Street West to 26th Street NW, as well as the reconstruction and paving of 26th Street NW from Eighth Avenue West to First Avenue NW. 

Estimated Construction Costs


  • $3.1 million

Project Schedule


  • Begin Date: October 2017
  • End Date: October 2018
  • Project Complete: 40%

Road Closures


  • Eighth Avenue NW is closed to through traffic from 26th Street NW to Ninth Street NW until August 1. Local traffic is allowed on the road.

Completed Work

  • All underground utilities
  • Embankment
  • Lift forcemain
  • Kost ponds pumped
  • West Fargo 5th addition

Current Work


  • Project on hold due to permits

Upcoming Work

  • Outfall installation
  • Stablization
  • Punchlist